CBS Liberec – progress of construction

In the first half of February the fitting of insulation has begun, at present part of the facade has been finished including the final plasterwork. The next step will be the fitting of external blinds and deassembling of the scaffolding in this part of the building.  The structure of the stainless steel roof of the terrace has been installed in the backyard. Interior plaster is finalized on the fifth floor and is in progress on the fourth and third floor. The flooring by CemFlows systém has been finished on the fifth floor and the installation of electrics, water supply, sewerage and heating is in progress on the other floors. The heat exchanger station is supposed to be fitted for mid-February and than the heating on the fifth floor could be activated. Construction continues smoothly due to schedule.